BMP Park Project Status

 

Below is a timeline status of the BMP Project

    • 2003 – 2005: Township sub-watershed modeling and prioritizing effective sites for reducing pollutants and volume of stormwater runoff; resulted in selection of Township-owned property for demonstration project.
    • 2006: Preliminary characterization of soil conditions within the proposed project area for soil type, depth to bedrock, and infiltration potential.
    • 2007: Detailed soil characterization (test pits, infiltration tests) by Cahill Associates.
    • 2007 – 2008: Develop designs and bid specifications for four phases of BMP construction in the demonstration project area.
    • Phase I, Swale Infiltration System:
      • Grant for Construction Awarded – 2008
      • Pre-construction water rainwater sampling - Sept 2008 & Feb 2009
      • Contract for Construction Awarded – May 2010
      • Construction Completed – May 2010
      • Continue beautification/plantings through 2011
    • Phase 2A, Brookside Infiltration System: 
      • Grant for Construction Awarded – 2009
      • Pre-construction water rainwater sampling - Dec 2010
      • Contract for Construction Awarded – Spring 2011
      • Construction Completed – Spring 2011
      • Continue beautification/plantings through 2011
    • The design documents for Amphitheater Infiltration System (Phase 2B) and Hart Lane Infiltration System (Phase 3) have been completed.
    • An educational presentation, “Rainwater Awareness” was developed and delivered in the spring of 2010. Additional sessions are planned.
Springfield Township